Why Port Harcourt-Enugu Road has not been completed — FASHOLA

Nigerian building institute confers fellowship on FasholaBy Egufe Yafugborhi & Davies Iheamnachor

MINISTER of Works and Housing, Babatunde Fashola, yesterday, blamed the seeming gradual tempo of labor on the 42Km Port Harcourt-Enugu on a variety of challenges the Federal Government is tackling as work progresses.

Fashola in Oyigbo, Rivers State, throughout inspection of the Imo River to Eleme Junction of the highway highlighted insufficient funds, troublesome terrain, compensations to property homeowners to accommodate enlargement from 4 to eight lanes, and the dedication to ship high quality job to final the textual content of time amongst others because the challenges.

He additionally emphasised that authorities wouldn’t abandon work on the delicate undertaking on account of the risk posed by the worldwide pandemic, Corona Virus, until well being specialists advise in any other case.

Before Fashola’s appraisal, the Controller of Works, Federal Ministry of Works and Housing, Rivers State, Johnson Fadire, stated the unique highway constructed within the 70s with out drains needed to collapse over time as many builders constructed on the highway sides used to retain the water and the median to carry the water.

READ ALSO: FEC approves N867m Engineering Design for Kano–Abuja freeway

On the 7.5Km (4th Section) from Imo River to Eleme Flyover which Fashola inspected, Fadire stated works by China Civil (CCECC) was 50 p.c full, , expressing fear over lack of fund to compensate landlords of constructing to be demolished and burrow-pits to discharge water.

He stated: “Out of the seven sections of the road, we have paid compensation on five sections but we have not paid for two. The last two kilometres we cannot go there now because we have not paid and that is where more demolitions were made.”

On his half, Fashola, stated, “As the highway that hyperlinks the entire 5 states of the South East to the South South by way of Port Harcourt, primarily, we’re constructing on water on a lot of this Port Harcourt-Enugu Road, so it’s a really difficult atmosphere to construct infrastructure.

“We wish to construct greater, wider and safer highway right here. Our design is to ship eight lanes from what was 4 on this half. Buildings should go. These are challenges notably the folks of Aba and Port Harcourt should respect on why this highway is taking a while to construct.

“You have a number of sand filling occurring right here. The highway is dug as much as properly over  two meters, all of the dangerous soil being eliminated throughout all the size in eight locations. That’s the logistics of the work actually, every lane occasions eight. That’s a number of dredging work away from right here.

“All civil issues and some civic obligations have to be discharged before we get the road. While government does its part, we appeal to residents, citizens, state and local governments to also help us mobilise their people to a sense of civic responsibility and cooperation.”

On Covid-19 possible impacting on the undertaking’s 2021 supply goal, Fashola stated, “There are all the time trade-offs when human survival is challenged. First, growth and survival generally can not go collectively. The trade-off is to decide on survival first. And these are the alternatives our authorities and the President is making.

“You have seen the cut in fuel price, certain expedition cuts by the Minister of Finance. The contractor is on site. As long as construction is able to go on, under advice by the scientists and health experts, people will continue to work because this is where some earn their daily living.”

Fashola later moved to the Government House, Port Harcourt, the place he had a media guarded session with Governor Nyesom Wike of the state.